Week Commencing 01 May

  • Unit 7 HB40 repairs (sun-room).
  • Unit 7 plaster sun-room.
  • Unit 7 painting bathroom and sun-room.
  • Unit 7 tile replacement.
  • Slab preparation for membrane (cut out thread rod from steel grids and treat, leveling where needed, hydropoxy).
  • Unit 4 spooling repairs and steel treatment.
  • Painting of render (boiler room underside slab).

In the weeks ahead

  • Tiling works to start on unit 7 and 8 balconies
  • Reinstall steel screens on balconies
  • Reinstall electrics and tray table underside of slab
  • Powerpoint and light fitting in boilerroom to be installed 
  • Unit 4 concrete spawling works
  • Slip joint installed to chimney