Week commencing 5 February

  • Roof plumber completed changing northern niche box gutters.
  • Internal repairs to units 6, 10, 14, 29 and 31 completed.
  • Demolished tiles for new concrete hob at unit 10 balcony.
  • Continued painting on Campbell and lower Campbell St facade.
  • Commenced installation of roof parapets aluminium capping and pool deck flashing.
  • Continued cleaning windows and balconies at lower Campbell and Campbell St facade.

In the week ahead

  • Install formwork and pour new concrete hob to unit 10 balcony.
  • Roof plumber to complete installation of northern niche new roof box gutters.
  • Complete Equitone FC sheet installation on eastern deck face and install pool cupboard doors.
  • Continue changing roofing screws to thicker gauge.
  • Complete roof parapet capping installation.
  • Continue internal repairs at units 7, 8, 12, 29, 30 and 31.
  • Complete painting Campbell and lower Campbell St facade and on Roof Top.