Week commencing 05 June

  • Completed water testing.
  • Continued with tiling of podium slab.
  • Started installation of expansion joint to tiles in communal area.
  • Started tiling courtyards.
  • Hydro epoxy unit 1's new slab and hob.
  • Completed screed to unit 1's courtyard.
  • Cut out slab for unit 1's drain pipe.
  • Cut out slab and repair to pressure pipe fill with blue metal and concrete.
  • Install unit 1's drain pipe in slab and infill with blue metal and concrete.
  • Continue with HB40 works in garage area.
  • Backfill pathway to podium slab ready for new slab and stairs.
  • Clean site to keep surrounding neat and tidy.

In the week ahead

  • Continue with HB40 works in garage area and individual garage's.
  • Backfill entrance way ready for new slab.
  • Form new walkway and stairs(weather dependant).
  • Finish tiling podium slab and start entranceways and courtyards.
  • Continue with render works in garage area.
  • Continue installation of expansion joint to tiles.
  • Screed the rest of unit 1's courtyard.
  • Apply Ardex WPM300 to unit 1's screed.
  • Cut out slab for pressure pipe repair and fill with blue metal and concrete.
  • Install unit 1's new drainage pipe fill with blue metal and concrete.
  • Clean site.