Week commencing 1 August

  • Site office set up
  • Temporary power boxes connected in roof area
  • Swing stage 1 installation started 
  • Dilapidation survey started

In the week ahead

  • Inspection to be performed by consultant engineer
  • Dilapidation continues
  • Helifix and spalling investigation and repairs
  • Emergency evacuation plan to be issued and bin areas to be alloted