Week commencing 9 May

  • Floor Grind Unit 2

  • Complete scaffolds unit 1, 2, 3 and 4

  • Remove drummy render to units

  • Concrete Unit 10 landing and remove drummy render 

  • Demo Unit 1, 3 and 4 terrace stairs

 

In the week ahead

  • Start unit 2 and 3 door alterations

  • Build hobs and start waterproofing deck and cavity 

  • Unit 10 works, order skylights

  • Demo unit 4 terrace

  • Remove all drummy render from unit 1 and 4

  • Render units 1,2,3, and 4