Week commencing 16 May

  • Start unit 2 and 3 door alterations

  • Build hobs and start waterproofing deck and cavity 

  • Unit 10 works, order skylights

  • Demo unit 4 terrace

  • Remove all drummy render from unit 1 and 4

  • Render units 1,2,3, and 4

 

In the week ahead

  • Unit 2 rooftop services to be moved. 

  • Unit 2 rooftop coving and then waterproofed

  • Unit 2 and 3 door jambs to be installed

  • Unit 2 and 3 landings to be waterproofed.

  • Unit 1 and 4 door alterations.

  • Render units 1,2,3,4, and 10

  • Unit 10 a/c services snorkel