Week commencing 23 May

  • Unit 2 rooftop services to be moved. 

  • Unit 2 rooftop coving and then waterproofed

  • Unit 2 and 3 door jambs to be installed

  • Unit 2 and 3 landings to be waterproofed.

  • Unit 1 and 4 door alterations.

  • Render units 1,2,3,4, and 10

  • Unit 10 a/c services snorkel 

 

In the week ahead

  • Complete render patching 

  • Complete cavity waterproofing 

  • Complete cavity brickwork

  • Waterproof Unit 2 roof

  • Waterproof Unit 1 - 4 spiral terraces

  • Measure colourbond cappings

  • Finish door jamb Units 1 - 4 

  • Finish control joints