Week commencing 30 May

  • Complete render patching 

  • Complete cavity waterproofing 

  • Complete cavity brickwork

  • Waterproof Unit 2 roof

  • Waterproof Unit 1 - 4 spiral terraces

  • Measure colourbond cappings

  • Finish door jamb Units 1 - 4 

  • Finish control joints 

 

In the week ahead

  • Complete Stage 1 render

  • Second layer of membrane waterproofing for Unit 2

  • Finish waterproofing for Unit 1 and 2

  • Work on cavity for Unit 4

  • Screed small balconies for Unit 1, 2, 3 and 4 

  • Finish Stage 2 scaffolds 

  • Unit 8 roof works 

  • Unit 5, 6, 7 and 8 small balconies works