Week commencing 6 June 

  • Complete Stage 1 render

  • Second layer of membrane waterproofing for Unit 2

  • Finish waterproofing for Unit 1 and 2

  • Work on cavity for Unit 4

  • Screed small balconies for Unit 1, 2, 3 and 4 

  • Finish Stage 2 scaffolds 

  • Unit 8 roof works 

  • Unit 5, 6, 7 and 8 small balconies works 

 

In the week ahead

  • Remove perimeter flashing, Stage 2 

  • Start with door hob and door jambs, Stage 2 

  • Finish Unit 10 western facade render 

  • Finish all Stage 1 rendering 

  • Hang all doors, Stage 1 

  • Finish storm moulds Stage 1 & 2 

  • Survey test, Stage 2 

  • Remove drummy render, Stage 2 

  • Floor grind Unit 8 roof 

  • Start cement render coving to Unit 8 roof 

  • Electric power boards to Stage 2 

  • Paint sample to Unit 1 front door