Week commencing 13 June 

  • Remove perimeter flashing, Stage 2 

  • Start with door hob and door jambs, Stage 2 

  • Finish Unit 10 western facade render 

  • Finish all Stage 1 rendering 

  • Hang all doors, Stage 1 

  • Finish storm moulds Stage 1 & 2 

  • Survey test, Stage 2 

  • Remove drummy render, Stage 2 

  • Floor grind Unit 8 roof 

  • Start cement render coving to Unit 8 roof 

  • Electric power boards to Stage 2 

  • Paint sample to Unit 1 front door 

 

In the week ahead

  • Complete all Stage 2 door alterations, install door jambs

  • Waterproof all Stage 2 small landings 

  • Remove all cover flashings and render 

  • Start rendering stage 2 

  • Paint Unit 1 south facade 

  • Install Unit 10 sky lights hydropoxy screed to Unit 1, 3 & 4 

  • Start roof demolition to Unit 1 & 2 

  • Complete Unit 8 roof preparation