Week commencing 20 June 

  • Complete all Stage 2 door alterations, install door jambs

  • Waterproof all Stage 2 small landings 

  • Remove all cover flashings and render 

  • Start rendering stage 2 

  • Paint Unit 1 south facade 

  • Install Unit 10 sky lights hydropoxy screed to Unit 1, 3 & 4 

  • Start roof demolition to Unit 1 & 2 

  • Complete Unit 8 roof preparation

 

In the week ahead

  • Complete demolition on Units 1 & 3 

  • Remove all membranes from Units 1 & 3 

  • Render coving on Unit 1 & 3

  • Continue priming Stage 1 units and complete Unit 1 facades 

  • Complete Units 7 & 8 door alterations 

  • Render Units 5, 6, 7 & 8 doors 

  • Complete the cover flashing demolition on Units 5, 6, 7 & 8 and render 

  • Order tiles