Week commencing 27 June 

  • Complete demolition on Units 1 & 3 

  • Remove all membranes from Units 1 & 3 

  • Render coving on Unit 1 & 3

  • Continue priming Stage 1 units and complete Unit 1 facades 

  • Complete Units 7 & 8 door alterations 

  • Render Units 5, 6, 7 & 8 doors 

  • Complete the cover flashing demolition on Units 5, 6, 7 & 8 and render 

  • Order tiles 

 

In the week ahead

  • Complete all render demolition 

  • Finish rendering works 

  • Install windows in Unit 10 

  • Waterproof stage 2 small balconies 

  • Finish 1st coat of membrane to units 1, 2, 3, and 4

  • Change plywood covers to f. c sheet 

  • Prepare roof for balustrades after engineer plans

  • Unit 7 door works 

  • Start to fit architectural quads to new timber door jambs