Week commencing 4 July

  • Complete all render demolition 

  • Finish rendering works 

  • Install windows in Unit 10 

  • Waterproof stage 2 small balconies 

  • Finish 1st coat of membrane to units 1, 2, 3, and 4

  • Change plywood covers to f. c sheet 

  • Prepare roof for balustrades after engineer plans

  • Unit 7 door works 

  • Start to fit architectural quads to new timber door jambs

 

In the week ahead

  • Waterproofing in Unit 5, 6, 7 & 8 spiral balconies 

  • Torch membrane waterproofing starts on Units 3, 4 & 5 roofs

  • Build landings to Unit 1, 3 & 8 

  • Electricians to remove lights on facade

  • Finish storm moulds 

  • Finish rendering to Unit 5

  • Finalise balustrade details 

  • Bag 13 tons of sand