Week commencing 18 July

  • Screeding in Units 5, 6, 7, and 8 completed 

  • Started tiling to Unit 1, 2, 3 & 4 

  • Started waterproofing to Unit 10 western facade, primed and first coat applied

  • Started internal paint to Unit 10 

  • Render repairs to all facade repairs - 90% complete 

  • Unit 7 door works 

  • Architrave works in Unit 7 & 8 

  • Completed storm moulds

In the week ahead

  • Complete tiling and grout 

  • Complete Unit 10 works 

  • Start Unit 10 staircase paint strip 

  • Complete render 

  • Set out and build balustrade plinth 

  • Start roof terrace waterproofing 

  • Paint new door jambs 

  • Complete all control joints and silicone 

  • Finish all architraves