Week commencing 25 July

  • Completed tiles on Units 1, 2, 3, 4, 5, 6, and 8. Unit 7 tiles on order

  • Grouted tiles on 1, 4, 5, 6, and 8 

  • Unit 10 Western waterproofing completed 

  • Unit 1 and 3 torch membrane started 

  • Painters have started to prepare for painting on door jambs

  • Render patching complete 

In the week ahead

  • Complete Sika joint works and control joints 

  • Stage 2 Unit facade, wash, prime and first coat 

  • Start balustrade preparation 

  • Finish architraves on remaining doors

  • Paint all entrance doors