Week commencing 1 August

  • Unit 5, 6, 7, and 8 pressure cleaned and ready to prime

  • Entrance door primed

  • All doors architraves completed

  • Control joint works continued

In the week ahead

  • Complete control joint works

  • Start roof preparation for balustrades 

  • Complete waterproofing 

  • Prime and apply first coat of membranes to facades of units 5, 6, 7, and 8 

  • Paint entrance doors