Week commencing 8 August

  • Formwork to Unit 2 and 3

  • Poured concrete on Unit 2 plinths 

  • Water blasting done  Unit 5, 6, 7, and 8

  • Primed and first coat applied on facade membrane

  • Primed entrance doors

In the week ahead

  • Complete plinths to Units 1, 2, 3, and 8

  • Paint all entrance doors

  • Complete control joints, cut and fill

  • Start rendering top of parapet walls

  • Start Unit 10 stairwell wall paint removal

  • Reinstate Unit 10 plumbing 

  • Install new rain heads