Week commencing 15 August

  • Completed painting entrance doors 

  • Completed extra plinths for balustrades

  • Raised brickwork on parapets of Units 1, 2, 3 and 8 

  • Unit 10 Western facade plumbing 

  • Started to install new rain heads 

  • Waterproofing continued and plinth constructed 

  • Grinding back existing paint on top on the parapet to prepare for rendering 

  • Rendering started on Units 4 and 5 

In the week ahead

  • Complete waterproofing 

  • Flood test roof terraces Units 1, 2, 3, and 8 

  • Start screeding works

  • Continue to render top of parapet - complete 50%

  • Paint all door jambs 

  • Membrane coat Unit 4 & 5 and complete facade waterproofing