Week commencing 12 June

  • Continue with HB40 works in garage area and individual garage's.
  • Backfill entrance way ready for new slab.
  • Form new walkway and stairs(weather dependant).
  • Continue tiling podium slab and start entranceways and courtyards.
  • Continue with render works in garage area.
  • Continue installation of expansion joint to tiles.
  • Screed the rest of unit 1's courtyard.
  • Apply Ardex WPM300 to unit 1's screed.
  • Cut out slab for pressure pipe repair and fill with blue metal and concrete.
  • Install unit 1's new drainage pipe fill with blue metal and concrete.
  • Clean site to keep surrounding neat and tidy.

In the week ahead

  • Continue with render in garage and render band at base of dividing walls.
  • Continue with tiling courtyards and entrance ways.
  • Grout courtyard and entrance way tiles that have been laid.
  • Apply WPM300 to unit 1's new screed.
  • Pour entrance way slab and stairs.
  • Pour new stair detail at rear entrance.
  • Strip formwork.
  • Continue with installation of expansion joint to podium slab tiles.
  • Complete concrete pour over pressure pipe.
  • Apply WP[M300 and WPM002 to bricks for capping tile.
  • Clean site.