Week commencing 28 November

  • Continuation of office fit out
  • Application and protection of 'peel away' paint system to western and southern elevation
  • Initial investigation of parapet structure and flashing 

In the week ahead

  • Stripping and cleaning 'peel away' applied to western and southern elevation
  • Application of peel away to eastern elevation
  • Commence demolition to pool area as advised
  • Removal of steel fins