Week commencing 12 September

  • Biscuit bricks installation in Stage 1 (long drop & short drop)
  • Level 8 concrete slab repairs 
  • Brick pointing in Stage 1 (long drop & short drop)

In the week ahead

  • Biscuit bricks to stainless steel angle levels (long drop Level 6, 9, and 10)
  • Brick pointing in Stage 1 (long drop & short drop)
  • Sealants to flashings (long drop)
  • Acid washing 
  • Flashings and rendered slab paintings (long drop)
  • Stage 2 swing stage set up 
  • Replace corner bricks in Stage 2 (short drop)