Week commencing 19 September

  • Biscuit bricks to stainless steel angle levels (long drop Level 6,9, and 10)
  • Long & short drop wall brick pointing 
  • Adhesives to flashings (Long drop)
  • Acid washing 
  • Flashings and rendered slab painting (long drop)
  • 3rd swing stage set up (Stage2)
  • Stage 2 replacing corner bricks 

In the week ahead

Stage 1

  • Acid washing 
  • Adhesives to flashings to continue 
  • Brick pointing touch up jobs 
  • Level 3 brick opening to inspect cavity 
  • Flashing and render sections cleaning and painting 
  • Possible swing stage dismounting depending on the outcome of cavity inspection 
  • Level 3 brick opening for cavity inspection
  • Level 8 spalling repairs 
  • Level 4, 7, 10, and 11 spalling repair, HB 40 application for biscuit bricks and biscuit bricks to corner 

Stage 2

  • Level 1-13 inspection with consultant
  • Level 4, 7, 10, and 11 openings for work