Week commencing 26 September

Stage 1

  • Acid washing 
  • Sikaflex flashings 
  • Brick pointing touch up jobs 
  • Level 3 brick opening to inspect cavity 
  • Flashings and render sections cleaning and painting 
  • Level 8 spalling repairs 
  • Level 4, 7, 10, and 11 spalling repairs, HB 40 application for biscuit bricks and bricks to corners

Stage 2 

  • Level 1-13 inspection with consultant 
  • Level 4, 7, 10, and 11 openings 

In the week ahead

Stage 1

  • External skin opening Level 3, bricking up opening 
  • Brick pointing and acid washing to Level 2 openings
  • Level 8 making good of HB 40 corner bathroom window and repair 
  • Level 10 and 11 reinforcement bars cleaning, HB 40 application and biscuit brick corners 
  • Brick pointing and acid washing 

Stage 2

  • Helifix ties & external skin opening from Level 5 to 13 
  • Painters to Unit 16 bathroom TBC