Week commencing 10 October

Stage 1

  • Partial swing stage dismounting 
  • Rendering around external window
  • Paint to lead flashing and corner window lintels 

Stage 2

  • Helifix ties application
  • Opening top levels and repairs to slabs
  • Reinforcement cleaning and HB 40 application

Stage 3

  • Swing stage installation 
  • Inspection of balconies, dilapidation survey and repairs as required 
  • Unit 16 bathroom painting works
  • Unit 22 fix living room wall damages and paint

In the week ahead

Stage 2

  • Flat render wall painting 
  • Slab fixing Level 9 - 11
  • Biscuit bricks to openings in Level 10 - 13
  • Level 6 - 8 biscuit openings 

Stage 3

  • Balcony spalling repairs (Level 8, 9, and 10)

Interior

  • Unit 22 fix living room wall damages and paint