Week commencing 24 October

Stage 2

  • Slab fixing Level 2, 3, 4, 5, 6, 9, 10, and 11
  • HB 40 to opened slabs 
  • Biscuit bricks trimming to the HB 40 slab build out size 

Stage 3

  • Balconies spalling repairs, HB 40 application and make good works (Level 9)
  • Removing drummy render, preparing for renderers & painters 

Stage 4

  • Inspection in walls and first openings 

Interior

  • Unit 22 fix living room wall damages and paint 

In the week ahead

Stage 2

  • Clean reinforcement bars and HB40 to opened slabs (entire wall E)
  • HB 40 slab build out (entire wall E)

Stage 3

  • Balconies: Rendering, painting, bricks to Level 9 corner balcony

Stage 4

  • Level 10, 11, 12 brick openings, slab openings and steel cleaning

Interior

  • Unit 22 render finish to living room 
  • Paint patches (from damages) on living room wall