Week commencing 31 October

Stage 2

  • Clean reinforcement bars and HB40 to opened slabs (entire wall E)
  • HB 40 slab build out (entire wall E)

Stage 3

  • Balconies: Rendering, painting, bricks to Level 9 corner balcony

Stage 4

  • Level 10, 11, 12 brick openings, slab openings and steel cleaning

Interior

  • Finish render to Unit 22 living room 
  • Paint patches (from damages) on living room wall 

In the week ahead

Stage 2

  • HB 40 slab build out (entire wall E)
  • Cut the biscuits to wall E openings

Stage 3

  • Balconies:
    • Finish painting to ceilings and hobs
    • Make good to level 9 balcony
    • General cleaning

Stage 4a (wall G / 30% wall H)

  • Clean and prime reinforcement bars 
  • Apply HB40 to spalling
  • HB40 build out for biscuit bricks 
  • Cut the biscuits to wall openings

Stage 4b (wall H)

  • Swing stage and landing platform establishment 
  • Inspection of wall to be performed by Dave Wright and James Reynolds
  • Helifix application
  • First biscuit openings