Week commencing 07 November

Stage 2

  • HB 40 slab build out (entire wall E)
  • Cut the biscuits to wall E openings

Stage 3

  • Balconies:
    • Finish painting to ceilings and hobs
    • Make good to level 9 balcony
    • General cleaning

Stage 4a (wall G / 30% wall H)

  • Clean and prime reinforcement bars 
  • Apply HB40 to spalling
  • HB40 build out for biscuit bricks 
  • Cut the biscuits to wall openings

Stage 4b (wall H)

  • Swing stage and landing platform establishment 
  • Inspection completed by Dave Wright and James Reynolds
  • Helifix application
  • First biscuit openings

In the week ahead

Stage 2 (Wall E)

  • Biscuit bricks to Wall E
  • Brick pointing
  • Acid clean walls
  • Make good windows and walls
  • Start painting flashings and window lintels

Stage 3 (Wall F)

  • Start painting balcony side slabs and hobs 
  • Balcony general cleaning and make good

Stage 4a (wall G / wall Ha)

  • Biscuit bricks
  • Brick pointing
  • Acid clean walls
  • Make good windows and walls
  • Start painting flashings and window lintels

Stage 4b (wall Hb)

  • Repair spalling concrete and clean steel to exposed slabs
  • Remove deteriorated brick brackets
  • Make good concrete slab in preparation for HB40 build out