Week commencing 14 November

Stage 2 (Wall E)

  • Biscuits bricks
  • Brick pointing
  • Wall acid cleaning
  • Make good windows and walls
  • Start painting flashings and window lintels

Stage 3 (Wall F)

  • Start painting balcony side slabs and hobs 
  • General cleaning of balconies - make good

Stage 4a (Wall G/Ha)

  • Biscuit bricks
  • Brick pointing
  • Wall acid washing
  • Make good windows and walls 
  • Start painting flashings and window lintels

Stage 4b (Wall Hb)

  • Fix exposed slab spalling
  • Remove deteriorated brick brackets 
  • Make good concrete slab for HB40 build out
  • HB40 build out application

In the week ahead

Stage 2

  • Dismount swing stage 

Stage 4a

  • Dismount swing stage 

Stage 4b

  • Finish biscuits bricks on flat walls
  • Mortar application and brick pointing
  • Acid wash walls and make good flashings
  • Level 10 balcony, HB40 application to spalling
  • Level 12 balcony, make good concrete spalling
  • Level 9 balcony, make good concrete spalling
  • Level 8 balcony make good concrete spalling and replace cracked corner bricks 
  • Level 7 balcony replace cracked corner bricks 
  • Level 6 make good concrete spalling and replace cracked corner bricks to balconies
  • Level 5 make good concrete spalling and replace cracked corner bricks to balconies

Stage 11 (North)

  • Swing stage installation
  • Dave Wright and James Reynolds wall inspection
  • Helifix ties application
  • First brick openings

Stage 10 (North)

  • Erect ground area protection (windows, walkways near main entrance and Unit 1 entrance)
  • Swing stage installation
  • Dave Wright and James Reynolds wall inspection
  • Helifix ties application
  • First bricks opening

Roof area making good/preparation for common access