Week commencing 21 November

Stage 2

  • Dismount swing stage

Stage 4a

  • Dismount swing stage

Stage 4b

  • Finish biscuit bricks on flat walls
  • Apply mortar and commence brick pointing
  • Acid wash walls and make-good flashing
  • Level 5
    • make-good concrete spalling
    • replace cracked balcony corner bricks 
  • Level 6
    • make-good concrete spalling
    • replace cracked balcony corner bricks 
  • Level 7
    • replace cracked balcony corner bricks 
  • Level 8
    • make-good concrete spalling
    • replace cracked balcony corner bricks 
  • Level 9
    • make-good concrete spalling
  • Level 10
    • HB40 application 
  • Level 12
    • make-good concrete spalling

Stage 10

  • Erect ground floor protection 
  • Install swing stage 
  • Wall inspection
  • Helifix tie application
  • Commence first brick openings

Stage 11

  • Install swing stage 
  • Wall inspection
  • Helifix tie application
  • Commence first brick openings

Roof Area

  • Gerneral make-good and preparation for common access

In the week ahead

Stage 4b

  • Acid clean biscuit bricks 
  • Make-good flashing
  • Make-good HB40 application to balcony slab
  • Render HB40 patches
  • Paint walls above windows, flashings and sides of balconies
  • General cleaning 
  • Relocate swing stage

Stage 9

  • Plan swing stage 
  • Assemble landing platform and erect ground floor protection
  • Install swing stage 

Stage 10

  • Biscuit bricks to be opened 
  • Concrete slab repairs (remove old brackets and expose any deteriorated steel for repairs)
  • Concrete slab HB40 build out 
  • Cavity investigation and corner flashings to Level 12

Stage 11

  • Biscuit bricks to be opened 
  • Concrete slab repairs (remove old brackets and expose any deteriorated steel for repairs)
  • Concrete slab HB40 build out 
  • Cavity investigation and corner flashings to Level 12
  • Erect ground level protection