Week commencing 05 December

Stage 10

  • Level 10 led flashing installation
  • Brick pointing
  • Wall acid cleaning
  • Prepare walls for rendering

Stage 11

  • Level 11 led flashing installation
  • Biscuit brick to openings
  • Brick pointing
  • Wall acid cleaning
  • Prepare walls for rendering

Stage 9

  • Finish ground level protection
  • Wall inspection with Dave Wright
  • First biscuit brick openings

Roof area

  • Prepare area for painters
  • Install protection for swing stage

In the week ahead

Stage 10

  • Level 10 led flashing make good
  • Corner biscuit brick installation
  • Render flat wall openings

Stage 11

  • Level 11 led flashing make good
  • Corner biscuit brick installation
  • Render flat wall openings

Stage 9

  • Finish Helifix installation
  • Finish installation of attachment bracket for swing stage
  • Spalling repairs

Stage 2

  • Vent cover replacement

Stage 1

  • Site office awning cleaning job

 

Finish painting to lower ground garages 