Week commencing 28 November

Stage 4b

  • Acid wash biscuit bricks
  • Make-good flashing
  • Make good HB40 to balcony slabs
  • Render HB40 patches
  • Prepare for painters - paint flat walls above the windows, flashings and sides of balconies
  • Cleaning 
  • Swing stage relocation

Stage 10

  • Biscuit bricks to be opened
  • Concrete slab fixing - remove old brackets and expose any deteriorated steel for repair
  • Concrete slab HB40 build out
  • Level 12 corner flashing and cavity investigation

Stage 11

  • Biscuit bricks to be opened
  • Concrete slab fixing - remove old brackets and expose any deteriorated steel for repair
  • Concrete slab HB40 build out
  • Level 12 corner flashing and cavity investigation
  • Erect ground level protection 

Misc

  • Prepare lower ground and roof area for painting

In the week ahead

Stage 9

  • Finish ground level protection
  • Wall inspection with Dave Wright
  • First brick biscuit openings

Stage 10

  • Installation of Level 10 led flashing 
  • Brick pointing
  • Acid wash walls
  • Prepare wall for rendering

Stage 11

  • Installation of Level 11 led flashing 
  • Biscuits to openings
  • Brick pointing
  • Acid wash walls
  • Prepare wall for rendering

Roof Area

  • Prepare for painters
  • Erect protection for swing stage machinery