Week commencing 09 January

Continued previously staged works. 

In the week ahead

Stage 10a

  • Replaced Level 9, 11 & 12 lead flashing 
  • Clean exposed reinforcement bars
  • HB40 application
  • Biscuits to openings
  • Render patches to flat walls

Stage 9

  • Remvoe render to Level 5 flat wall 
  • Expose and clean reinforcement bars
  • HB40 application to openings

Stage 8

  • Reinforcement bars to be exposed, cleaned and patched with HB40 (LVL 13)
  • HB40 build out to all levels

Painting

  • Ground garage frames
  • Stage 11 ground level flat wall
  • Roof top tower painting