In the week ahead

Stage 9

Complete corner lead flashing replacement on LVL 13

Complete HB40 repairs on flat wall, LVL 13

Render to flat walls

Painting of flashings and

Swing stage to be relocated

Timber awning to be pulled down, general cleaning in front area

Stage 7A

Spall inspection on existing openings and required repairs

Jackhammering, Reo bars cleaning ,  ZinciPrimer application

Stage 7B

Wall inspection

Biscuits openings

Spall inspection on existing openings and required repairs

Jackhammering, Reo bars cleaning ,  ZinciPrimer application

Stage 6

New stage preparation & establishment