Week commencing 15 May

  • Start waterproofing podium slab, entrance ways and courtyards.
  • Complete brick work on driveway wall.
  • Brick work to base of the slab in unit 1 for new slab to go on top inside.
  • Start forming new slab and stairs at entrance way(weather dependant).
  • Continue with HB40 works to garage area and individual garage areas.
  • Water test for those done with waterproofing.

In the week ahead

  • Complete waterproofing installation (weather dependant).
  • Start flood testing waterproofing.
  • start tiling podium slab.
  • continue with HB40 work in owner's garage area and main garage area.
  • hydro epoxy balustrade hob with Ardex WPM300 AND Ardex WPM002.
  • complete installation of pressure seal to hob for waterproofing termination.
  • complete excavation works to drive way and backfill to height.
  • start slab works in unit 1's garage for drainage pipe (if variation is approved).
  • expose pressure pipe (if variation is approved).