Week commencing 18 April

  • Complete deck B timber frame and decking and reorganise walkway and site fence to allow for fire exit from block B
  • Paint reverse side of decking for units 5 & 6
  • Remove decking to Units 5 & 6 make ready for reinstated decking deliver timber

In the week ahead

  • Continue to treat underside of decking
  • Treat the top side after the installed decking has dried out and completed.
  • Waterproofing removal and WB30 Continues around Units 21 and 30.