Week commencing 26 September 

  • Scaffolds set up completed
  • Site office set up completed 
  • Move sliding door from Units 401 and 402 started
  • Planter boxes emptied
  • Started demolition of balconies in Unit 401 and 402
  • Skip bin arrangements done 
  • Render stripping started

In the week ahead

  • Remove all sliding doors from Unit 401 & 402 
  • Disconnect air conditioning units in 401 & 402 
  • Complete planter box demolition in Units 401 & 402 
  • Start balcony demolition (tile and screed) and temporary waterproofing 
  • Strip all steel render angles and prepare for patching 
  • Strip all drummy render and prepare for patching