Week commencing 4 October 

  • Installed fall arrest system for demolition works for resident safety (extra plywood hoardings)
  • Removed sliding doors from Unit 401 & 402 
  • Unit 204 Eastern sliding door removed 
  • Continued with Level 4 planter boxes works - 80% demolished 
  • Continued with removal of steel render angles - 80% completed 
  • Temporary weather proof protection over sliding doors

In the week ahead

  • Complete Level 4 planter boxes
  • Start Level 4 tile and screed demolition followed by substrate resurfacing and temporary waterproofing 
  • Mount air conditioning units in Unit 401 & 402 
  • Finish area with Dulux 968 Acra-Tex Elastomeric 201 high build 
  • Finish render stripping and prepare for patch render 
  • Level 2 Unit 204 works - remove tiles and Western sliding door