Week commencing 17 October 

  • Demolished all Western balconies on Level 3 & 4 
  • Floor grinding on Level 4 - 90% completed 
  • Unit 301, 302, and 303 resurfacing works - 90% completed 
  • Render angles - 90% removed 
  • Test patches on Level 4, render and high build membrane 

In the week ahead

  • Complete Level 3 Western balconies 
  • Complete Level 4 balconies resurfacing 
  • Install puddle flanges to door wastes on Level 3 & 4