Week commencing 07 November 

  • Cured Level 4 screeds
  • Cut expansion joints to unit 401 screed
  • Removed sliding doors:
    • Unit 303 East balcony
    • Unit 102 West balcony
  • Demolished:
    • Unit 304 East balcony
    • Unit 303 East balcony 
  • Resurfaced Unit 304 East balcony
  • Rendered Units 401 and 402 large balconies
  • Primed Level 4 screeds
  • Adjusted hob heights on Units 401 and 402
  • Prepared for screed on Level 3

In the week ahead

  • Screed Level 3 balconies
  • Finish Level 3 & 4 rendering
  • Waterproof Level 4