Week commencing 14 November 

  • Prepared Level 4 for waterproofing

  • Fixed and sealed colour matched angles to the top of Level 4 hobs

  • Screed to Level 3 balconies

  • Poured 4 plinths around down pipes on western Level 4 balconies

  • Rendered Level 4 (approx. 95% completed)

  • Rendered Level 3 (approx. 75% completed)

  • Unit 204 balcony - tiles layed, planter wall painted, removed all material and protection

  • Started Unit 102 works - removed row of tiles for isolated works

In the week ahead

  • Start Level 3 waterproofing

  • Finish Level 4 waterproofing and start tiling 

  • Prime Level 3 screeds

  • Finish Level 3 & 4 render and continue to Level 2

  • Screed 101 planter and 204 planter