Week commencing 21 November 

  • Waterproofed Level 4

  • Flood tested Level 4

  • Adjusted Level 3 hobs and installed water stop angle

  • Prime Level 3 screeds

  • Screed Unit 204 planterbox

In the week ahead

  • Waterproof Level 3

  • Install sliding doors to Unit 403 and Level 3

  • Start internal make-good on Unit 402 and Level 3