Week commencing 28 November 

  • Tiled floors to Level 4 balcony 

  • Waterproofed and flood tested Level 3 eastern and western balconies

  • Tiled Level 3 western balconies

  • Filled control joints and rendered down to Level 1

  • Removed bolts from Unit 402

  • Installed sliding doors to Units 301 (west), 302 (west), 303 (west) & 402

  • Start internal make-good to Units 303 & 402

In the week ahead

  • Paint Level 4

  • Finish skirting tiles on Levels 3 & 4

  • Waterproof Unit 101 & 204 planterboxes 

  • Finish Unit 102 isolated waterproofing 

  • Install sliding doors to Unit 304, 401 and all eastern side to Level 3 

  • Paint Unit 402 internal 

  • Continue internal makegood on Level 3

  • Install A/C Units on the 8th to Units 401 & 402

  • Finish render in balconies down to Level 1