Week commencing 05 December

  • Installed sliding doors to Units 402, 301, 302 & 303
  • Installed four A/C to Units 401 & 402
  • Installed 90% of torched membrane to Units 101 & 204 planter boxes
  • Floors tiled to Level 3 eastern balconies
  • Skirting's tiled to Level 4
  • Fit skirting boards to units 301, 302, 303, 304 & 402
  • Internal make good to Unit 303, approx. 95% complete
  • Installed stainless steel anchors to Unit 402 living balcony
  • Completed butynol membrane

In the week ahead

  • Start painting from Level 4
  • Continue and finish internal make good to Level 4
  • Install top rail to Level 4 
  • Complete all waterproofing
  • Install Unit 102 sliding door and lay tiles
  • Finish tiling
  • Start Unit 202 east balcony isolated works