Week commencing 12 December

  • Commenced painting and application of elastomeric to western facade
  • Completed 2 coats to balcony soffits and downpipes
  • Skirting tiles layed
  • Down pipes attached to Unit 401 & 402 (east)
  • Near completion of level 4 grouting (Unit 401 living room balcony remaining)
  • Completed Unit 402 plaster and painting works
  • Commenced Level 3 plaster and painting works
  • Waterproofed and flood tested planter boxes to Units 101 & 204
  • Planter boxes lined with drainage cells, coreflute and geotexile protection
  • Planters filled with blue metal and socked aggflow line (soil to fill)
  • Commenced Unit 202 eastern balcony isolated works 
  • Commenced removal of materials from site

In the week ahead

  • Complete all painting by Tuesday
  • Prepare site management handover
  • Complete all internal makegoods
  • Install top rail to Units 401 & 402 balconies
  • Complete Level 3 grouting
  • Lay screed and tiles to Unit 102 and finish works
  • Complete Unit 202 east balcony
  • Fit new external lights
  • Remove all remaining items from scaffold
  • Pressure clean
  • Dismantle scaffold