Week commencing 09 January

  • Site clean-up
  • Paint rear Level 3 balconies
  • Removed plywood protection from ground floor scaffold
  • Removal of ground floor render angles
  • Cleaned, re-fit bedroom carpets and removed floor protection
  • Touch-up missing sika control joints
  • Tilers cleaned expansion joints

In the week ahead

  • Remove scaffold
  • Continue with unit 302 internal make good
  • Check all residents internals are completed
  • Make good tile grout
  • Finish unit 202 east balcony isolated work