Week commencing 06 February

  • Completed polyurethane control joints on ground floor
  • Fixed security blocks to fixed panel sliding doors, Units 301, 303, 304, 401, 402
  • Removed stairwell lights and installed temporary lights
  • Waterproofed behind lights
  • Made alterations to unit 303 carpet to fit like new
  • Painted unit 303, 304 sliding door skirting
  • Pressure cleaned unit 101, 102 balcony
  • Pressure cleaned stairwells
  • Pressure clean footpath
  • Pressure cleaned garage toilet

In the week ahead

  • Finish painting
  • Install stairwell lights and 1st floor lights
  • Remove site office
  • Install tread plates to sliding doors in units 303, 304, 401, 402
  • Remove materials
  • Finalize Defects