Week commencing 19 June

  • Continue with render in garage and render band at base of dividing walls.
  • Continue with tiling courtyards and entrance ways.
  • Grout courtyard and entrance way tiles that have been laid.
  • Apply WPM300 to unit 1's new screed.
  • Pour entrance way slab and stairs.
  • Pour new stair detail at rear entrance.
  • Strip formwork.
  • Continue with installation of expansion joint to podium slab tiles.
  • Complete concrete pour over pressure pipe.
  • Apply WPM300 and WPM002 to bricks for capping tile.
  • Clean site to keep surrounding neat and tidy.

In the week ahead

  • Start painting in garage area.
  • Finish screed in unit 1 courtyard and hydropoxy.
  • Install butanol waterproofing weather dependant.
  • Install angle down side wall of unit 1 and hydropoxy slab and angle.
  • Continue with tiling of entrance ways and courtyards and grout.
  • Continue installing expansion joint to podium tiles.
  • Start installing expansion joints to courtyard tiles and entrance ways.
  • Pour footing for planter box.
  • Clean site.