Week commencing 21 August

  • Removed pallets, materials and tools from site. 
  • Repaired defects.
  • Completed installation of expansion joints.

In the week ahead

  • Complete Maxbuild works.
  • Remove remaining tools and material from site.
  • Repair defects and Clean up.