Week commencing 21 March

  • Finish demolition works 
  • Complete water testing
  • Conduct survey and mark-up floor plan to determine where the leaks are 

In the week ahead

  • Water test of deck area to Building A 
  • Commence tile break out to units 21 to 30
  • Deliver and stack timber supplies