Week commencing 22 May

  • Started flood test.
  • Start tiling podium slab.
  • Continue with HB40 work in owner's garage area and main garage area.
  • Hydro epoxy balustrade hob with Ardex WPM300 AND Ardex WPM002.
  • Complete installation of pressure seal to hob for waterproofing termination.
  • Complete excavation works to drive way and backfill to height.

In the week ahead

  • Complete installation of waterproofing.
  • Complete installation of pressure seal for waterproofing termination.
  • Complete water test to podium slab and courtyards.
  • Continue with installation of tiles to podium slab.
  • Start rendering balustrade hob.
  • Start installation of reo form and pour unit 1's slab.
  • Continue with HB40 works in garage area and individual garages.
  • Complete build of brick piers.
  • Check measures for balustrade.
  • Start installation of reo and form ply for entrance way and step.
  • Start slab works in unit 1's garage for drainage pipe (if variation is approved).
  • Expose pressure pipe (if variation is approved).